ICE Krakow continues to grow

In spite of the Christmas break, the last month of the old year proved very fruitful. Construction works above the “0” Level in all segments of the facility were continued. Construction works have been performed up to and even above the 2+ Level  in segments of the back-up facilities and the Auditorium Room – works have been performed to the most advanced extent in these parts of the facility.


The construction of the external walls and staircase walls has been performed up to the +1 Level in the foyer segment visible from the side of Al. Konopnickiej. Less spectacular but equally important work was performed below the 0 Level  – the removal of the ties stabilising the cavity wall was completed and holes remaining after the disassembly were sealed.

 