June at the ICE Kraków construction site

Below you will find the next summary of the construction work progress at the ICE Kraków. We invite you to read the newest report.

Construction work progress at the ICE Kraków Congress Centre, as of 30th June 2014

In June at the Congress Centre construction site, work was underway in the backroom facility segment, on power supply installation (lighting). Flooring was laid on all levels, wall tiles were laid, bathroom fittings and fixtures were installed and the doors fitted. Electroacoustic systems were being installed in the Chamber Hall and the Conference Hall Complex. Work on the sound-proof wall and ceiling cladding in both above-mentioned halls was underway.

In the Auditorium Hall segment, finishing works and the work on stage machinery (upper and lower) continued, as well the raised floor and installation of electroacoustic systems. Sound-proof wall cladding began to be laid.

Plastering work and weak-current installation were underway in the Theatre Hall, as well as sound-proof wall cladding (completed) and the execution of electroacoustic systems.

In the Foyer segment, work on weak-current systems was underway The laying of screed floors continued, along with the construction of drywalls and suspended ceilings, as well as the fitting of glass partitions. Work on the underground levels (garages) was practically finished – only the floor is still to be laid and park sites marked.

The roof rounding work was in progress. Throughout the facility, water, hydrant , sanitary installation, sanitary, fat, rainwater and sprinkler sewage systems, district heating (installation of heaters, air curtains, heating and ventilation units and controls still to be finished), cooling, ventilation and air-conditioning, fire ventilation were also completed (with the exception of the light fixtures and control systems). Work on the glass part of the building’s façade continued. Lifts and door-frame woodwork construction were being installed. The fitting of bathroom furniture and in-built furniture began. The work on the planning of the area around the facility, lighting and blinds control system continued and the work on the building management system (BMS).

Here you can find the newest photos.

 

To see the newest photos of the construction site, please go to "See ICE" section.

 

 

Media contact

All journalists interested in the events organized in the ICE Kraków, please contact

Michał Zalewski
Media contact

Tel.: 0048 513 099 671 / 0048 12 354 23 20
press@icekrakow.pl

Contact